Installation Diagrams
| Typical Installation without Bench Tank |
|
The above diagram is intended only for Illustration
purposes and
cannot be used in place of the detailed instructions |
| Detailed Side-Wall Chimney Installation |
|
| The proper installation of the chimney is critical to insure adequate
draft for the INOV8 waste oil furnace. The ultraviolet sensor used
in this burner will cause a shutdown if smoke, fumes or ash generated
by poorly burning waste oil accumulates enough to restrict the view
of the flame. The stack must be installed the proper distance above
the roof line to avoid down drafts. Insufficient chimney height or
excessive turns in the flue will decrease the draft to such extent
that the furnace safety system will cause a safety shutdown. Also,
make sure the flue pipe connected to the furnace can be easily removed
& swung out of the way for ease in cleaning. |
| Oil Storage Systems |
|
| Many operational problems can be eliminated if proper care is taken
in setting up an oil storage system. All waste oil contains substantial
amounts of water and sludge, both of which settle to the bottom of
a tank over a period of time. A storage system that allows sufficient
settlement time will provide trouble free operation. A two-tank system
is recommended allowing one tank to settle while drawing from the
other. A one-tank system will work, but the floating oil pickup assembly,
that is supplied with the INOV8 furnace, must be used. |
| Bench Tank Setup |
|
| Bench tanks are available in sizes ranging from 280 gallons to 500
gallons. Our standard is a 300-gallon tank with steel supports, which
holds the INOV8 furnace 8 feet above the floor. Installations using
the bench tank are easier than those without the tank because of the
ease in mounting the furnace versus hanging and the short distance
for running the oil supply line. The bench tank comes fully supplied
with all the necessary fittings for a complete installation. Many
states and cities have additional regulations regarding the storage
of waste or other fuels which may require stricter measures. It is
very important to check with your local fire inspector, or proper
authority, or a qualified tank installer regarding the requirements
in your area. |
The following four items must be adhered to throughout the installation
and ongoing operation of the INOV8 furnace:
- This furnace is listed for commercial and/or commercial use
only. It cannot be used for residential or any other unauthorized
purpose.
- This equipment is tested to UL Standard 296A (the U.S. waste
oil standard), to Canadian Standard Association, standard B141.4
by Underwriters's Laboratory of Canada and is listed with the
European Economic Community with a CE registration number 3884/97.
This product is approved to burn the following fuels: crankcase
oils, gear box oils (85 - 140 wt), up to 175 wt heat transfer
oils, transmission and hydraulic oils, vegetable oils, and oils
with up to 10% gasoline. DO NOT attempt to burn other liquids
without checking with INOV8.
- The assembly, installation, adjustment and maintenance of this
equipment must be done by an INOV8 certified (or otherwise qualified
installer), in accordance with the instructions in the furnace
installation manual, and in compliance with all federal, state
and local regulations regarding environmental control, fuel storage,
fire and electrical standards.
- The INOV8 equipment must be operated to the settings established
in the furnace installation manual and display on the furnace.
|
|